Construction on the Exposition Line began in the fall of 2006. Work
currently underway includes utility and corridor improvements on Flower
St. from Washington Blvd to 23rd St. in Downtown LA. Those activities
include relocation of waterlines, gas, power, cable TV, sewer and storm
drains as well as roadway improvements, traffic control and street lighting.
Utility relocation and trench construction from Jefferson Blvd. and
Flower St. to Vermont Blvd. and Exposition Blvd. began in the summer
of 2007. Over the winter and spring of 2008, street closures will
be required to perform the installation of the top deck of the trench.
The entire trench construction will take 13 months to complete. The
west end of the alignment will be used as a work and storage area for
the contractor and be the location where the pre-cast deck girders will
be manufactured. All construction work will be performed in accordance
with City of Los Angeles’ rules and regulations.
View
Construction Activity Archives
2008
05/02/08 - Girder Installation (Temporay Closure of Figueroa St and Exposition Blvd) - Downtown Corridor
04/22/08 - Flower Street Closure, Storm Drain Installation - Downtown Corridor
04/04/08 - K-Rail Installation - Mid-Corridor
04/04/08 - Full Street Closure, Girder Installation - Downtown Corridor
03/21/08 - Full Street Closure, Girder Installation - Downtown Corridor
03/14/08 - REVISED Storm Drain Installation - Downtown Corridor
03/12/08 - Fence Installation and Securing of ROW - Mid-Corridor
03/11/08 - Girder Installation (Flower Street) - Downtown Corridor
03/07/08 - REVISED Fence Installation and Securing of ROW - West End
03/05/08 - Fence Installation and Securing of ROW - West End
03/05/08 - Drain Storm Installation - Downtown Corridor
02/26/08 - Tree and Track Removal - Mid-Corridor & West End
02/08/08 - Supplemental Tree Removal Notice - Mid-Corridor
01/28/08 - Revised Track and Tree Removal - Mid-Corridor
2007
12/26/07 - Mid-Corridor Tree and Track Removal
12/02/07 - Utility Relocation / Flower Street Closure
11/13/07 - Flower Street Closure
11/04/07 - Water Line Tie-In
11/12/07 - Utility Relocation - Gas Company
10/22/07 - Pipeline Trestle Removal
09/28/07 - Girder Installation
09/07/07 - Closure of Pardee Way
08/29/07 - Street Closure on Figueroa
08/27/07 - Re-Alignment of Exposition Blvd
08/01/07 - Tree Removal
07/09/07 - Drilling Soil and Grout
07/09/07 - Installation of Piles
07/02/07 - Cast Girder Construction Yard
05/07/07 - Utility Relocation
04/09/07 - Storm
Drain Work/Street Closure
04/09/07 - Utility
Relocation
02/11/07 - Storm
Drain Work
01/11/07 - Soil
Testing
01/08/07 - Temporary
Tree Relocation
2006
10/14/06 - Underground
Pipeline Removal
10/13/06 - Construction
Begins On Flower Street
08/28/06 - Field
Investigations Begin
The timeline will be available shortly. |